Foundation Design Philosophy for Horizontal
Vessel
In
this page I will talk about Horizontal vessel / Horizontal Drum
equipment foundation load calculation. Following is a picture
of Horizontal vessel / Drum:
Now
you will follow the following steps to start the foundation load
calculation and design:
Step-1
: Review
of vessel drawing (Vendor Equipment Drawing)
You
need to review Vessel drawings from foundation design point of view and
check whether you have all the following information:
Vessel
Erection weight (De1):
Vessel
Empty weight (De2):
Vessel
Operating weight (Do):
Vessel
Hydrotest weight (Dt):
Wind
Shear and Moment in transverse direction
Seismic
Shear and Moment in transverse direction (if the Project
site is at Seismic zone)
Vessel
operating temperature and confirm with Mechnaical discipline
Total
length of vessel and spacing of saddle supports
Vessel
Center of Gravity location with respect to saddle
Anchor
bolt location on fixed and sliding saddle
Detail
of equipment saddle (fixed and sliding)
Step-2
: Verification of
foundation location, elevation
and external fittings loads
You
need to review Plot plan, Equipment location drawings and 3
-D Models and
check whether you have all the following information:
Verify the area available
for foundation.
Verify
Foundation location and Elevation
Pipe
supports and Nozzle loads on Equipment (Dp)
Location
and size of Platforms around the vessel
Locations
of underground pipes
Electrical
and Instrument duct banks
Locations
and extent of adjacent foundations
Verify
the location and extent of new/existing foundations not shown in 3D
model or plot plan.
Step-3
: Description of Foundation Loads:
Please
follow this section to understand the different loads on foundation:
Vessel Erection weight
(De1): The erection
weight is the fabricated weight of
the vessel, plus internals, platforms, etc., that are actually erected
with the
vessel. Data from Equipment drawing.
Vessel Empty weight (De2): The
empty weight is the in-place weight of the
completed vessel, including the fabricated weight of the vessel, plus
the
weight of internals, piping, insulation, and platforms, but excluding
the
weight of fluids or products which will be contained in the vessel
during
operation. Data from
Equipment drawings.
Vessel Operating weight
(Do):
Vessel Empty weight (De2) + Weight of Fluid inside the
vessel. Data from Equipment drawings.
Vessel Hydrotest weight(Dt): Vessel
Empty weight (De2)
+ Weight of test water
Pipe
supports and Nozzle loads on Equipment(Dp): Please
Coordinate with the Pipe Stress Group for
determination of nozzle loads and loads due to pipe supports
attached to the vessel.
Wind
Shear and Moment (W):
You will find this load data in vendor drawings.
However, you have to calculate this load based on project design basis.
During wind load calculation, you need to consider the pipes and
platforms attached with the vessel. Transverse and longitudinal wind
load shall be calculated per design project criteria. No allowance
shall be made for shielding of winds by nearby equioment. The
calculated design moments and shears due
to wind load should be compared to those shown on the vessel
drawings and maximum loads shall be used for foundation design.
Seismic Shear and Moment
(E) (if the Project site is
at Seismic zone): You
will find this load data in vendor drawings. However, you have to
calculate this load based on project design basis. During seismic load
calculation, you need to consider the pipes and platforms attached with
the vessel. The longitudinal seismic
force shall be resisted by the fixed end pier only unless the piers are
tied
together by tie beams below the base plates.Transverse seismic forces shall be resisted by both
piers using saddle
or base plate reactions as the basis for computing base shear.The
calculated design moments and shears due
to seismic should be compared to those shown on the vessel
drawings and maximum loads shall be used for foundation design.
Thermal
Load (T): The thermal load
is defined as the load which results from thermal expansion or
contraction of
the exchanger/vessel in the longitudinal direction.The maximum thermal force is equal to the
maximum static friction force (frictional resistance) acting at the
equipment
sliding support before the saddle begins to move.The frictional resistance equals the
coefficient of friction (see project design criteria) times the
vertical support reaction.
The
thermal load
considered in foundation design shall be the smaller of the following:
The
maximum pier reaction at the
sliding end times the coefficient of friction of the sliding surfaces
The force required to deflect each
pier one-half the amount of the total thermal expansion between
supports
(assuming thermal loads of equal magnitude, but opposite directions,
act on
each pier).
Generally, for
short piers, the frictional force discussed in item (a) above governs
the
design.
Step-4
: Load combinations for foundation sizing /
Pile loads
and Foundation design:
You
need to create the load combination per your project design criteria.
However, I have created this load combination based on ACI 318:
Load
combination for Foundation sizing and Pile load calculation
(un-factored load calculation):
LC1:
Do + Dp
+ T
LC2:
(De1 or De2)+ Wind
LC3:
De2+ Seismic
LC4:
Do + Dp + Wind + T
LC5:
Do + Dp + Seismic + T
LC6:
Dt + 025*Wind
Load
combination for Pedestal and Foundation design (factored load
calculation):
LC7:
1.4*(Do + T + Dp
)
LC8:
0.75 [1.4 De2
(or 1.4 De1)] +1.6 Wind
LC9:
1.2 De2+1.0 E
LC10:
0.75 (1.4 Do +1.4 T +
1.4 Dp)
± 1.6 Wind
LC11: 1.2 (Do +T + Dp)
+ 1.0 E
LC12: 0.75 (1.4 Dt) + 1.6 (0.25 W)
The
weight of the foundation and of the soil on top of the foundation shall
be included as dead load in all of these load combinations.
Step-5
: Anchor Bolt Check:
Maximum
shear and tension on anchor bolt shall be calculated based on above
load combinations and shall be compared with project acceptable value.
Anchor bolt embedment length shall be checked per any project approved
code (ex: ACI 318 appendix-D).
Step-6
: Pedestal Sizing
and reinforcement:
Unless
controlled by other factors, the minimum pier
dimensions in each direction should equal to the dimensions of the base
plate
plus 100mm.Piers
shall be sized
in 50mm increments.The
minimum
thickness of the pier should be approximately 10% of the pier height,
with a
minimum of 250mm.
Pier size should be adjusted to ensure the
factored
vertical force on the pier does not exceed the value of 0.1Agfc¢
(Refer ACI 318 section 10.3.5)
Piers should be designed as axially loaded
cantilever
flexural members
When
the
size of the pier cannot be adjusted and the value of the
axial load exceeds 0.1Agfc¢, the
piers should be designed as compression members subjected tocombined
flexure and compressive axial load.
For piers with slenderness ratio equal to or
exceeding
22, moment magnification effects should be considered (refer section
10.13 of ACI 318).In
calculating
the slenderness ratio, a "K" factor of 2 should beused.The P-M column interaction
check may also be considered in pier design.
Shears on
piers along both the longitudinal and transverse directions of the
equipment
shall be checked per code requirements (refer ACI 318, Chapter 11).
Reinforcement
should normally be arranged symmetrically.Both the fixed end and sliding end piers shall
be sized and reinforced
identically.For
pier height less than
7 feet, the vertical reinforcement may be extended from the
foundation
with no dowels being required.
A double
tie shall be placed at the top of piers, spaced 50mm and 125mm below
the
top of concrete (or below the bottom of grout), to protect the top of
concrete
piers against cracking.
Step-7 :
Slide plate :
Slide plates are
placed at the sliding end pier to allow longitudinal movement of
exchangers and
vessels due to the thermal growth.The
steel slide plate on the sliding end is generally coated with Dow
Corning G-n
Metal Assembly Paste or similar lubricant in order to reduce the
coefficient of
friction.Slide
plates should be
galvanized or painted to prevent corrosion.
For
large
movements and/or heavy horizontal vessels, it may be
necessary to use slide
plates with low coefficient of static friction, such as lubrite,
teflon,
etc.Design of
lubrite and teflon slide
plates shall be in accordance with the recommendations of the slide
plate
manufacturer, as the coefficient of static friction varies with the
temperature
and pressure at the bearing surface.
Typical
coefficients of friction (m) are as follows
0.15,
for mild steel slide plates coated with Dow Corning G-n Metal Assembly
Paste
0.20, for mild steel to mild steel
without lubricant
0.06, for teflon slide plates with
bearing pressure over 100 psi
Now from
above steps, you have learnt the following:
Different
types of loads on foundation
Different
criterias for the pedestal sizing
Maximum
tension and shear force on each anchor bolt
A
sample load combinations.
To complete
the foundation design, your work will be to create following
calculation sheets:
A
calculation sheet for anchor bolt embedment length check (ex: ACI 318
appendix-D).
A
calculation sheet for foundation sizing (considering soil bearing
pressure, Sliding, Buoyancy and overturning) or pile load (tension,
compression and shear on each pile) calculation and check with soil
consultant for acceptable values.
A
calculation sheet for foundation and pedestal reinforcement calculation
per your project design criteria.
For
typical foundation for a Horizontal Vessel click here I
hope this page will be very helpful to you to understand the basic
foundation loads of a Horizontal Vessel.
Please
donate generously for more development of this site:
Copyright 2009.
All rights reserved. Please do not print or copy of this page or any
part of this page without written permission from Subhro Roy. Disclaimer:
This page is prepared based on experience on Civil Engineering Design.
All definitions and most of the explanations are taken from different
text books and international design codes, which are referenced in the
contents. Any similarity of the content or part of with any company
document is simply a coincidence. Subhro Roy is not responsible for
that.